BRAY FILM STUDIO

The work involved includes excavation/reinstatement in the carriageway/footpath/verge for the installation of a High Voltage Electric Cable to reinforce the Existing Network along the roads mentioned above with the use of temporary traffic signals as per permits imposed by the local authority.

We will try to minimise any disruption to you and your access onto your properties but whilst the works are in place. We will maintain access to your properties and driveways however when the excavation is being completed this may not be possible. During the evening or out of working hours access will be maintained. If you have any special requirements on any given day, please speak directly to the team on site who will assist you. Only the roads above will be affected by this work.

We intend to undertake our works between the hours of 07-00 and 18-00. Weekend Working will be required on some of the main roads and to speed the programme up. Weekend working from 07-00 to 17-00 Saturdays and 09-00 to 16-00 Sundays.

The Project Manager for these works and first point of call is: Tristan Howe; 07932 350605 or on the office number – 02477170505.

Should you have any concerns or questions prior to or during the works please do not hesitate to contact us.

PROGRAM OF WORKS

M4 Bridge Crossing supervision required to complete this. 18th January 2023 – Completed

Highfield Lane Permit Start date 23rd January 2023 – 11th February 2023 – Completed

Forest Green Road. Start date 15th March 2023 – 14th April 2023

Ascot Road. Start date 27th March 2023 – 6th April 2023

Paley Street Start date 15th May 2023 – 31st May – Completed

Fifield Road. Start date 29th May 2023 – 29th June 2023 – Completed

Windsor Road. Start date 9th January 2023 – 20th February 2023 – Completed

ROAD CLOSURES

Start date 11/02/2023 – 19/02/2023 – Cannon Lane under railway bridge TTRO – Completed

Start date 01/03/2023 – 28/03/2023 – Coningsby Lane- To be completed by 15/03/23

Start date 01/03/2023 – 08/03/2023 – Church Hill – Completed

Start date 10/04/2023 – 28/04/2023 – Forest Green Road – Completed